Temporary road closure - Waitangi Parade

On display until 12 December 2026, 05:00 PM

Council contractor Loaders will be carrying out wastewater pipeline installation works on Waitangi Parade, Mowhanau, involving the installation of approximately 125 metres of new pipeline and three manholes.

Work is scheduled to begin on Monday, 16 November 2026 and is expected to take around three weeks to complete.

During this time, access to individual properties may be limited and vehicle access may not always be possible while construction is underway. Residents are asked to speak with the site crew before entering the work area so safe access can be arranged where possible.

A residents-only access sign will be in place at the entrance to the road. We apologise for any inconvenience and appreciate your patience while this work is completed.